TITLE Supreme Court Decision 99Da40418 delivered on June 15, 2001 [full Text]
Summary
Whether, in a large-scale construction project performed through subcontracts, a construction subcontract is deemed to have been executed only when there is an agreement not only as to the construction cost but also as to other material matters such as the specific preliminary work for and the implementation method of the construction project and the general conditions pertaining to the payment method of the construction cost, etc.